Free press releases distribution network?

Agency / Source: McCarthy Building Companies, Inc.

Check Ads Availability|e-mail Article


Are you the owner of this article?, Turn it PREMIUM with your LOGO instead - and make it 3rd party Ads-Free! within the next hour!



Structural Steel Work Completes on Torrance Memorial Medical Center New Patient Tower - Construction is one step closer to completion on the new $450 million Torrance Memorial Medical Center Patient Tower - McCarthy.com
Structural Steel Work Completes on Torrance Memorial Medical Center New Patient Tower

 

PRZOOM - /newswire/ - St. Louis, MO, United States, 2012/03/02 - Construction is one step closer to completion on the new $450 million Torrance Memorial Medical Center Patient Tower - McCarthy.com.

   
 
Your Banner Ad Here instead - Showing along with ALL Articles covering Construction/Architecture/Infra Announcements

Replace these Affiliate Programs at ANYTIME! Your banner here within the next hour. Learn How!


 

Located on the existing medical center site at 3330 Lomita Boulevard in Torrance, Calif., the project reached a major milestone when construction workers placed the final piece of structural steel on the 398,350-square-foot facility.

McCarthy, is serving as general contractor for the project which began construction in February 2010. During the steel erection phase, iron workers from Herrick Steel placed 5,820 pieces of structural steel within three months in order to build the frame for the new tower.

The project team celebrated the topping out of structural steel on February 23, 2012 during a barbecue luncheon held for the construction workers and other project officials. Later that same day, more than 75 hospital guests were invited to sign the ceremonial steel beam, which was adorned with an American flag and evergreen tree, then lifted 270 feet high to the top of the structure.

“The evergreen tree symbolizes growth, life and good luck for the construction workers and future occupants, and the flag is a patriotic symbol that signifies the united effort by the project team,” explained McCarthy Project Manager Erik Chessmore. “Everyone involved on the project has worked closely and collaboratively to come this far, and construction is currently nine-days ahead of schedule.”

“This day marks a tremendous milestone in our community’s healthcare history and future,” said Craig Leach, president and CEO of Torrance Memorial Medical Center. “It has taken a community to raise this tower, and we want to express our tremendous gratitude for its continued contributions of time and money in its shaping. The tower’s leading edge design will help us facilitate the standard of care our growing community needs and deserves well into the future.”

The new hospital, which will replace Torrance Memorial’s original tower built in 1971, will feature the latest medical technologies, more beds and space and a modernized design. The seven-level patient tower will house 256 private rooms, 18 surgical and interventional treatment rooms as well as a basement with a central utility plant and a tunnel connecting the existing hospital to the new facility.

Designed by HMC Architects, the replacement hospital will serve as the new front door of the medical center, and the centerpiece of the campus. The entrance of the new tower is positioned at the end of a bustling outdoor plaza and leads to a bright and open lobby. An indoor-outdoor cafeteria, gift shop, admittance services, and a chapel will all be easily accessible on the first floor.

In addition to providing a state-of-the art medical technology, the tower’s patient-centered design addresses the comfort of visiting family members by incorporating family–friendly lounges and overnight spaces. Additionally, gently curved nurses’ stations will allow for better care and visibility of patient rooms. Outdoor gardens will be built between the new and existing facility providing a serene and healing space for patients, visitors and staff.

The tower’s exterior skin will be a combination of metal panel, precast concrete, plaster and curtain wall. The combination of materials for the tower’s façade not only responds to the correct solar orientation to reduce energy consumption, but it also gives the tower a contemporary and elegant aesthetic.

McCarthy is using a combination of delivery systems to construct the new facility. Design-assist is being incorporated to deliver the Mechanical, Electrical & Plumbing (MEP) systems, structural steel, and framing, while design-build is being used for the exterior skin, elevators and fire protection system. The construction team is also using NavisWorks 3-D project modeling for clash detection and coordination to assist with extensive MEP overhead and in-wall coordination, as well as seismic bracing, and exterior skin systems.

The project is scheduled to complete by November 2014 and open in spring of 2015.

About McCarthy
McCarthy Building Companies, Inc. (mccarthy.com) has been ranked among the top five national healthcare builders by Modern Healthcare since the magazine began its annual ranking more than 30 years ago. As the largest American-based healthcare builder in the country, the firm has completed over $2.4 billion in healthcare work in Southern California alone. In addition to Newport Beach, McCarthy has offices in San Diego, Sacramento and San Francisco, Calif.; Phoenix; Las Vegas; Dallas; Houston; St. Louis and Atlanta. McCarthy is 100 percent employee owned.

 
 
Your Banner Ad Here instead - Showing along with ALL Articles covering Construction/Architecture/Infra Announcements

Replace these Affiliate Programs at ANYTIME! Your banner here within the next hour. Learn How!


 

Agency / Source: McCarthy Building Companies, Inc.

 
 

Availability: All Regions (Including Int'l)

 

Traffic Booster: [/] Quick PRZOOM - Press & Newswire Visibility Checker

 

Distribution / Indexing: [+] / [Company listed above is a registered member of our network. Content made possible by PRZOOM / PRTODAY indexing services]

 
 
# # #
 
 
  Your Banner Ad showing on ALL
Construction/Architecture/Infra articles,
CATCH Visitors via Your Competitors Announcements!


Structural Steel Work Completes on Torrance Memorial Medical Center New Patient Tower

Company website links NOT available to basic submissions
It is OK to republish and/or LINK any newswire for any legitimate media purpose as long as you name PRZOOM - Press & Newswire and LINK as the source.
 
  For more information, please visit:
Is this your article? Activate ALL web links by Upgrading to Press Release PREMIUM Plan Now!
McCarthy |
Contact: Susan Garritano - McCarthy.com 
314-968-3300 x2241 sgarritano[.]mccarthy.com
 
PRZOOM / PRTODAY - Newswire Today disclaims any content contained in this article. If you need/wish to contact the company who published the current release, you will need to contact them - NOT us. Issuers of articles are solely responsible for the accuracy of their content. Our complete disclaimer appears here.
IMPORTANT INFORMATION: Issuance, publication or distribution of this press release in certain jurisdictions could be subject to restrictions. The recipient of this press release is responsible for using this press release and the information herein in accordance with the applicable rules and regulations in the particular jurisdiction. This press release does not constitute an offer or an offering to acquire or subscribe for any McCarthy Building Companies, Inc. securities in any jurisdiction including any other companies listed or named in this release.

Construction/Architecture/Infra via RSSAdd NewswireToday - PRZOOM Headline News to FeedBurner
Find who RetweetFollow @NewswireTODAY



Are you the owner of this article?, Turn it PREMIUM with your LOGO instead - and make it 3rd party Ads-Free! within the next hour!




Read Latest Press Releases From McCarthy Building Companies, Inc. / Company Profile


Read Construction/Architecture/Infra Most Recent Related Press Releases:

The VINCI Airports-ORIX-Kansai Airports Joint Venture is Named Preferred Bidder for the Kobe Airport in Japan
VINCI Energies Acquires Acuntia - A Leading Spanish Information and Communication Technology Company
HOCHTIEF and BAM Deutschland to Refurbish and Operate Future Berlin Base of Federal Ministry of Health
CIMIC's Thiess Awarded $650 Million Solomon Extension
VINCI Launches Leonard - The New Group-wide Platform Dedicated to Innovation, Foresight and Inventing the Group's Future Businesses
VINCI Construction Wins A New Contract for Line 15 South of the Future Grand Paris Express Transport Network
CIMIC’S CPB Contractors Wins $400m Airport Runway Works in JV
Eurovia Reinforces its Position as A Leading Highway and Motorway Maintenance Company
Steel Rebar Market Projected to be Resilient During 2017-2025 Reports Persistence Market Research
CIMIC's CPB Contractors Awarded Sydney Metro Works

Boost Your Social Network
& Crowdfunding Campaigns


LIFETIME SOCIAL MEDIA WALL
 
NewswireToday Celebrates 10 Years in Business
Find business coaching, life coaching, executive coaching and corporate coaching, best selling coaching books, ...



PREMIUM Members


Visit  Rapid Recovery

Visit  La Bella Bakery Artisan Bakery Arizona

Visit  NAKIVO, Inc.







 
  ©2017 PRZOOM — Limelon Advertising, Co.
Home | About PRZOOM | Advertise/Pricing | Contact | Investors | Privacy/TOS | Sitemap | FRANCAIS
newswire, PR press releases distribution service magazines engine news alert newsroom press room breaking news public relations articles company news alerts newswiredistribution ezine bizentrepreneur biznewstoday digital business report market search pr firms agencies reports distri-bution today investor relation successful internet entrepreneur newswire distribution prtoday.com freenewswiredistribution asianewstoday bizwiretoday USA pr UK today